TypeIDWhatOwnerRaisedDueBlockingStatusClosure condition
RequestRQ-001Please read the project files and help me develop the project based on the attached governance, I need your heMaster Brain2026-08-202026-08-20-ClosedThe thing Zaid asked for exists and is delivered
RequestRQ-002[Intake answers, given through the clarification tool] Class: STANDARD. Jurisdiction: VIC. Services: Core suppMaster Brain2026-08-202026-08-20-ClosedThe thing Zaid asked for exists and is delivered
Action owed by ZaidACT-001Confirm whether you will operate the business yourself full time, or fund it and employ a manager.Zaid2026-08-202026-08-27Finalising the base case in the financial model (ASM-011)OpenZaid has provided the input or made the decision
Action owed by ZaidACT-002Tell me the monthly cash you need to draw from the business, and from what month.Zaid2026-08-202026-08-27The runway number in REQ-SYS-07 (ASM-012)OpenZaid has provided the input or made the decision
Action owed by ZaidACT-003Tell me the maximum capital you are prepared to lose entirely.Zaid2026-08-202026-08-27The final GO / NO-GO framing in REQ-SYS-08OpenZaid has provided the input or made the decision
Action owed by ZaidACT-004Tell me whether you or a co-founder holds a relevant qualification or prior disability-sector experience.Zaid2026-08-202026-08-27Confidence in the trade study recommendation (ASM-013)OpenZaid has provided the input or made the decision
Action owed by ZaidACT-005Ask the NDIS Commission whether the 1 October 2026 SIL registration deadline applies to a new entrant or only to providers already operating.Zaid2026-08-202026-09-05The SIL branch of the trade study (ASM-009)OpenZaid has provided the input or made the decision
Action owed by ZaidACT-006Ask the NDIS Commission whether it charges its own application or certificate fee separate from the auditor's fee.Zaid2026-08-202026-09-05Completeness of the capital figure in REQ-SYS-01 (ASM-010)OpenZaid has provided the input or made the decision
Action owed by ZaidACT-007Obtain a written quote from at least two Approved Quality Auditors for a verification audit of your intended registration groups.Zaid2026-08-202026-09-20Tightening the capital band (SRC-034, SRC-035)OpenZaid has provided the input or made the decision
Action owed by ZaidACT-008Obtain an insurance quote for public liability, professional indemnity and management liability.Zaid2026-08-202026-09-20Confidence in the recurring cost figure (SRC-040)OpenZaid has provided the input or made the decision
Action owed by ZaidACT-009Ask one operating Victorian NDIS provider how many non-billable administration hours they spend for every billable hour they deliver.Zaid2026-08-202026-09-05The base case in the financial model, the service model recommendation, and the go/no-go itself (ASM-008)OpenZaid has provided the input or made the decision
ChangeCR-001Establish the project baseline: folder skeleton, registers, framing artefact, bounded authority table, requireMaster Brain2026-08-202026-08-20-ClosedImplemented, verified and synchronised
ChangeCR-002Correct the fully-loaded labour cost from $50.71 to $52.28 per hour by adding WorkCover (1.8%) and the VictoriMaster Brain2026-08-202026-08-20-ClosedImplemented, verified and synchronised
ChangeCR-003Withdraw the weekend and public holiday margin figures rather than publish extrapolated penalty rates.Master Brain2026-08-202026-08-20-ClosedImplemented, verified and synchronised
ChangeCR-004Correct twelve defects found by independent deliverable verification before delivery: DEF-004 to DEF-014. InclMaster Brain2026-08-202026-08-20-ClosedImplemented, verified and synchronised
ChangeCR-005Correct DEF-015 to DEF-019 — the defects the FIRST round of corrections introduced or left behind — and removeMaster Brain2026-08-202026-08-20-ClosedImplemented, verified and synchronised
ChangeCR-006File the Governance Standard inside the project as CI-001 and generate its two projections; add checker C32 soMaster Brain2026-08-202026-08-20-ClosedImplemented, verified and synchronised
DefectDEF-001The four prior working files state costs, timeframes and rates with no resolvable source, and several are now Master Brain2026-08-202026-08-20-ClosedCorrective action done AND independently verified
DefectDEF-002The first pass at the labour model treated base wage plus casual loading plus superannuation as a fully-loadedIndependent verifier V22026-08-202026-08-20-ClosedCorrective action done AND independently verified
DefectDEF-003Weekend and public holiday casual penalty rates could not be sourced and were extrapolated in the first pass.Independent verifier V22026-08-202026-08-20-ClosedCorrective action done AND independently verified
DefectDEF-004The study stated that employing a manager pushes break-even past 126 billable hours a month. That is the PAID-Independent verifier V32026-08-202026-08-20-ClosedCorrective action done AND independently verified
DefectDEF-005The support coordination six-month capital figure was overstated by $1,288 and did not reconcile with its own Independent verifier V32026-08-202026-08-20-ClosedCorrective action done AND independently verified
DefectDEF-006ASM-008 recorded the wrong consequence, with the wrong sign, for the project's most dangerous assumption.Independent verifier V32026-08-202026-08-20-ClosedCorrective action done AND independently verified
DefectDEF-007Three different open-item counts were published across the README, the dashboard and the metric lineage, causeIndependent verifier V32026-08-202026-08-20-ClosedCorrective action done AND independently verified
DefectDEF-008The Definition of Done and the Part I compliance audit overstated four lines, including recording an independeIndependent verifier V32026-08-202026-08-20-ClosedCorrective action done AND independently verified
DefectDEF-009The delivered workbook computed a different fixed-cost band from the study, because the low and high columns oIndependent verifier V32026-08-202026-08-20-ClosedCorrective action done AND independently verified
DefectDEF-010The workbook shipped with no cached formula values, so any reader without a calculation engine saw blank cellsIndependent verifier V32026-08-202026-08-20-ClosedCorrective action done AND independently verified
DefectDEF-011Four checkers asserted more than they tested, and their descriptions were quoted elsewhere as evidence.Independent verifier V32026-08-202026-08-20-ClosedCorrective action done AND independently verified
DefectDEF-012A Windows absolute path appeared in the delivered study, under a gate marked PASS for cloud portability.Independent verifier V32026-08-202026-08-20-ClosedCorrective action done AND independently verified
DefectDEF-013Four requirement statements carried unquantified qualifiers, and the checker's banned-word list was too narrowIndependent verifier V32026-08-202026-08-20-ClosedCorrective action done AND independently verified
DefectDEF-014The ISS register row was column-shifted, so the mitigation appeared twice and the status column held the ownerIndependent verifier V32026-08-202026-08-20-ClosedCorrective action done AND independently verified
DefectDEF-015The repaired open-items tile contradicted itself in one sentence: the headline said 26 and the breakdown printIndependent verifier V3, second pass2026-08-202026-08-20-ClosedCorrective action done AND independently verified
DefectDEF-016build_all.py hard-coded two absolute tool paths that exist only on the machine that built the project, and exiIndependent verifier V3, second pass2026-08-202026-08-20-ClosedCorrective action done AND independently verified
DefectDEF-017The claim-attribution checker accepted a wider set of references than the requirement it certified.Independent verifier V3, second pass2026-08-202026-08-20-ClosedCorrective action done AND independently verified
DefectDEF-018Two dashboard tiles shipped with no metric lineage entry, and the checker that certifies lineage never compareIndependent verifier V3, second pass2026-08-202026-08-20-ClosedCorrective action done AND independently verified
DefectDEF-019Four evidence records cited artefacts that did not exist, and fifteen attributed evidence to the verifier whosIndependent verifier V3, second pass2026-08-202026-08-20-ClosedCorrective action done AND independently verified
DefectDEF-020The Governance Standard itself — CI-001, the artefact the whole project is built to obey — was never filed insZaid2026-08-202026-08-20-ClosedCorrective action done AND independently verified
RiskRSK-001Mandatory registration reaches personal care and daily living supports in July 2027, ending the unregistered pStart the verification registration application in month 1, not month 6. The 4-6 month verification pathway (SRC-021) leaves margin against July 2027 only if it starts early.2026-08-202026-09-20Capital decisionZaidMitigated, or accepted by Zaid in writing
RiskRSK-002Approximately half of NDIS providers were loss-making in 2024-25 and 81% report current pricing is unsustainabModel overhead explicitly rather than assuming it away; keep fixed cost below $1,000 per month until the tenth participant; treat admin hours as a costed input, not a rounding error (ASM-008).2026-08-202026-09-20Capital decisionZaidMitigated, or accepted by Zaid in writing
RiskRSK-003The support coordination service line is the subject of an active government restructure into a navigator modeDo not build a business whose only revenue line is support coordination. Pair it with a second line, and re-check the navigator design position every quarter.2026-08-202026-09-20Capital decisionZaidMitigated, or accepted by Zaid in writing
RiskRSK-004The SCHADS classification used in the model could be wrong by one level.Have the classification confirmed by a workplace relations adviser before the first hire. Until then the model carries it as ASM-002 at Medium confidence.2026-08-202026-09-20Capital decisionZaidMitigated, or accepted by Zaid in writing
RiskRSK-005Wages fall due before NDIS or plan-manager payments arrive.Hold the working-capital figure as ring-fenced cash, separate from setup capital. Confirm actual payment terms with a plan manager before the first shift is rostered.2026-08-202026-09-20Capital decisionZaidMitigated, or accepted by Zaid in writing
RiskRSK-006Foundational supports and the Thriving Kids programme begin drawing participants out of the scheme from 1 OctoTarget adult participants with established plans rather than the children's cohort most exposed to the transition.2026-08-202026-09-20Capital decisionZaidMitigated, or accepted by Zaid in writing
RiskRSK-007The NDIS price limits used throughout the model were read from a summarising fetch of a 65-page PDF rather thaRe-read the raw 2026-27 support catalogue and reconcile the five price limits used before any of them is relied on commercially. This is BKL-001.2026-08-202026-09-20Capital decisionMaster BrainMitigated, or accepted by Zaid in writing
RiskRSK-008No Approved Quality Auditor publishes a fee, so the largest single setup cost is a consultancy's estimate.Two written auditor quotes (ACT-007) collapse this band before any capital is committed.2026-08-202026-09-20Capital decisionZaidMitigated, or accepted by Zaid in writing
RiskRSK-009Client acquisition depends on referral relationships with support coordinators and plan managers, and no publiFund the runway for six months of zero revenue as the planning case, not the worst case. Begin referral relationship building during the registration wait, not after it.2026-08-202026-09-20Capital decisionZaidMitigated, or accepted by Zaid in writing
RiskRSK-010OPPORTUNITY (upside). Mandatory registration in July 2027 will remove unregistered competitors from the personRegistering early converts RSK-001 from a threat into an advantage. This is the strongest argument in the study for acting now rather than waiting.2026-08-202026-09-20Capital decisionZaidMitigated, or accepted by Zaid in writing
IssueISS-001fairwork.gov.au, fwc.gov.au, sro.vic.gov.au and several ndiscommission.gov.au pages block automated fetching.Zaid2026-08-202026-09-20Confidence levelOpenResolved or accepted by Zaid
BacklogBKL-001Re-read the raw NDIS 2026-27 support catalogue and reconcile the five price limits used in the model.Master Brain2026-08-20-REQ-SYS-05OpenDone, or explicitly dropped with a reason
BacklogBKL-002Obtain a first-party read of the SCHADS MA000100 pay guide, including casual weekend and public holiday penaltZaid2026-08-20-REQ-SYS-05OpenDone, or explicitly dropped with a reason
BacklogBKL-003Confirm the Victorian payroll tax threshold and the disability-sector WorkCover industry rate from primary souZaid2026-08-20-REQ-SYS-05OpenDone, or explicitly dropped with a reason
BacklogBKL-004Locate a current Victoria-specific NDIS participant count; the figure in use is from 30 June 2025.Master Brain2026-08-20-REQ-SYS-04OpenDone, or explicitly dropped with a reason
BacklogBKL-005Build the SIL/SDA financial branch once property parameters are supplied.Master Brain2026-08-20-REQ-SYS-04OpenDone, or explicitly dropped with a reason
BacklogBKL-007Replace the hand-written SIL/SDA registration-pathway range in study Table 5.1 with a computed figure.Master Brain2026-08-20-REQ-SYS-01OpenDone, or explicitly dropped with a reason
BacklogBKL-008Add a checker that an evidence record may not assert proof for a requirement the independent verdict fails.Master Brain2026-08-20-REQ-CON-01OpenDone, or explicitly dropped with a reason
BacklogBKL-009Render BKL-002 and BKL-003 on the dashboard. They are counted in the open-item total but appear in no view.Master Brain2026-08-20-REQ-SYS-15OpenDone, or explicitly dropped with a reason
BacklogBKL-010Derive the objective status on the dashboard from the requirements that serve each objective, rather than declMaster Brain2026-08-20-REQ-SYS-15OpenDone, or explicitly dropped with a reason
BacklogBKL-006Re-run the whole source register before 2027-08-20.Master Brain2026-08-20-REQ-CON-03OpenDone, or explicitly dropped with a reason
DecisionDEC-001Project class is STANDARD.Zaid2026-08-202026-08-20-ClosedRecorded with alternatives, weights, scoring and sensitivity
DecisionDEC-002Legacy figures in the four prior working files are quarantined, not carried forward.Zaid2026-08-202026-08-20-ClosedRecorded with alternatives, weights, scoring and sensitivity
DecisionDEC-003Recommended service model: SUPPORT COORDINATION, with core supports as a close second.Zaid2026-08-202026-08-20-Parked-ZaidRecorded with alternatives, weights, scoring and sensitivity
DecisionDEC-004Registration strategy: trade unregistered from month one and register in parallel, targeting registration befoZaid2026-08-202026-08-20-ClosedRecorded with alternatives, weights, scoring and sensitivity
DecisionDEC-005SIL/SDA is excluded from the recommended path for a first-time entrant.Zaid2026-08-202026-08-20-ClosedRecorded with alternatives, weights, scoring and sensitivity